Project Updates
What’s going on behind the fence? Learn more about the latest progress as the new home of the GSE takes shape.
August–October 2024
- South building installation of windows and “glazed curtain wall” (exterior glass wall) nearing completion
- Grading of the sunken garden (north building) underway
- Wall layout and window restoration in the north building in progress
June–July 2024
- North building center core foundation complete
- Framing of the north building forum and staircases in progress
- Installation of walls and doors in the south building underway
- Installation of windows in the south building ongoing
March–May 2024
- North building interior demolition complete
- North building upgrade of foundation and substructure continues, along with shoring, structural support, and footings for the center core.
- Exterior wall framing underway for the south building, as interior wall layout continues
January–February 2024
- North building center core (former auditorium plus south-facing rooms) is removed to make way for construction of the forum.
- South building structural steel, metal decking, and steel stairway completed.
- South building interior wall framing begins.
October–November 2023
- Construction of the steel structure for the south building gets underway in early October, with placement of the final beam ("Topping Off") on October 31.
- Excavation for the sunken garden is completed.
- Shoring up of the north building begins, in preparation for reconfiguration of interior spaces.
August-September 2023
- Permits are issued by the county.
- Construction of the new south building begins!
- Dirt hauling from excavation work continues; excavation of the sunken garden begins.
- Rebar delivery and concrete pouring begin.
- Utility work continues along Lasuen Mall.
June-July 2023
- North building roof tiles are removed and salvaged for reinstallation later.
- An existing PG&E gas line needs to be relocated because it runs under the south building site.
- Utility work includes tie-ins to lake water for irrigation, replacing power lines, and adding hot water pipes.
- Asbestos abatement is completed in the north building.
In March of 2023, the building adjacent to the historic Barnum building was demolished (and a palm tree relocated!) to make way for construction of the new south building.